This week Danella mobilized a crew to begin work on the West Chester X01 project which runs along Matlack Street.
Work has begun on the corner of Nields Street and Matlack. The plan will be to work our way down Matlack to the corner of Rosedale, then complete the to the streets that intersect.
Friday, March 17th was the first section of new piping which was put in (approx. 120ft). Once the entirety of the main is installed Danella will begin working on the services.